A construction company that undertook a project for the City of St. John’s in preparation for the 2025 Canada Summer Games claims it was assured additional payment upon meeting specific deadlines. Dissatisfied with non-payment, the company has resorted to legal action to secure the funds.
In a lawsuit filed at the Supreme Court of Newfoundland and Labrador, Lindsay Construction alleges that in April 2023, they entered into a contract with the city to build the new track, turf, and training center, valued at $31,998,750 with HST included. The contract reportedly included financial rewards for timely completion, with a $500,000 bonus if the track, field, and turf were finished by Sept. 30, 2024.
Despite Lindsay Construction asserting the milestone achievement, the city has purportedly declined to honor the incentive. Seeking the $500,000, accrued interest, legal fees, and appropriate court remedies, the company is pursuing legal recourse.
The construction project, known as the Fortis Canada Games Complex, is a $34 million facility featuring a 400-meter, eight-lane track, FIFA-standard soccer turf, and an indoor training venue for amateur sports development.
Lindsay Construction contends that the milestone encompassed the track, grass field, and soccer turf, with a significant portion completed by the deadline. Challenges arose in completing the grass field due to adverse weather conditions impeding sod installation. The company alleges that delays caused by the city and uncontrollable weather conditions prevented full completion by the stipulated date.
Despite nearly two years of negotiation attempts, Lindsay Construction asserts not receiving the promised financial compensation, resulting in substantial losses and damages. No response had been provided by the city or the plaintiff’s legal representative, James MacNeil of BoyneClarke, as of the latest report. It is essential to note that none of the claims made have been verified in court.